1
|
- Passed in 1999-2000 school year in the amount of $2,000,000
- Expenses total $2,007,191
|
|
2
|
- Two new computer labs built at Taos High including a huge battery backup
system for the labs that was also connected to the server closet
- Air ventilation systems installed at other computer labs throughout the
district
- Total cost $347,000
|
|
3
|
- 650 Dell computers
- 250 HP laser printer / scanners
- 10 HP Color laser printers
- 15 InFocus computer projectors
- Tables for all the computers
- Total cost $1,214,088
|
|
4
|
- 2-3 years of toner for all laser printers was purchased and distributed
to each school
- Parts for rebuilding 200 machines, at the cost of $350 per machine, to
make an old case into a new computer were purchased. The computer technology class will
rebuild computers with these parts next school year.
- Total cost $156,049
|
|
5
|
- Microsoft Licensing for Windows XP and Office XP with Front Page and
Publisher
- Surf Control Internet filter
- Novell networking OS
- Total cost $72,530
|
|
6
|
- E-Rate match for $500,000 of Gigabit networking upgrades
- E-Rate match for T1 lines from Zianet
- Network switches for classrooms
- Cat 5E and Fiber Optic Cable
- E-Rate match for Network and Phone maintenance contracts
- Total cost $217,859
|
|
7
|
- Construction of labs at TMS and upgrades to existing electrical systems
and installation of air conditioning
- E-Rate match each year
- Network infrastructure upgrades
- Software licensing
- Computers, projectors, cameras, etc…
|
|
8
|
- 1 Computer Lab at Taos Middle School
- All labs, server rooms, and the Technology Office must have air
conditioning, not ventilation, and electrical system upgrades which
should include a large battery backup like the high school. There are still many classrooms that
are not suited to multiple computer use due to lack of outlets.
- Estimated cost $350,000
|
|
9
|
- Over the last 4 years, the average E-Rate match has been around $50,000
which pays for 10% of the cost of T1 Internet lines, Network equipment
which includes servers and switches, Network OS, Telephone T1 lines and
other telecommunication costs
- Estimated cost $200,000
|
|
10
|
- E-Rate has allowed us to buy enough fiber optic cable to run from the
High School to every other building site. Four runs from the high school: to
RES, TMS/CRAB, EGS/TES and ANS.
The E-Rate does not pay to install the cable. We must pay for that. Applications like video conferencing
would be possible with fiber.
Fiber would also cut phone network costs and reduce network
maintenance problems by consolidating servers to one location.
- Estimated cost $300,000
|
|
11
|
- Micro$oft Licensing will cost over $57,000 for the 03-04 school
year. This must be paid every
year by July 31.
- Anti-virus software will cost nearly $22,000 per year.
- EdGate, AutoCAD, BackUp Exec, District database, any network site
licenses such as Mavis Beacon or Jump Start titles, etc… must be paid
annually
- Estimated cost $450,000
|
|
12
|
- Replacement schedule for computers
- Digital video cameras
- Network security cameras
- InFocus Projectors and screens
- Wireless Laptop and Modular Technology labs
- Toner, CD-Rs, zip drives and disks, etc…
- The others total $1,300,000 leaving the amount of $700,000 for items
here and/or other needs
|